| Source: | All England Reporter |
| Publisher Citation: | [2005] All ER (D) 24 (Jul) |
| Neutral Citation: | [2005] EWCA Civ 814 |
| Court: | Court of Appeal, Civil Division |
| Judge: | Sir Andrew Morritt V-C, Dyson and Thomas LJJ |
| Representation | Stephen Furst QC and Tim Lord (instructed by Davies Arnold Cooper) for the appellant. |
| Roger ter Haar QC and Alastair Walton (instructed by Lovells) for the respondent. | |
| Judgment Dates: | 16 June 2005 |
Catchwords
Building contract - Subcontractors - Interim certificate - Accrual of cause of action - Whether claim to have sum included in final certificate in respect of work or events for which sum should have been included in interim certificate fresh cause of action.
The Case
The cause of action in respect of an engineer's failure to include a sum in an interim certificate was not the same as the cause of action in respect of the failure to include a sum in the final certificate, even if the two sums happened to be the same.
Practice Areas
If you are a LexisLibrary subscriber you can read more about this case here.
Lexis®Library
- An Official transcript is the final version of the judgment prepared by shorthand writers. LexisLibrary contains all judgments from the High Court and aboveView Judgment
- The All England Law Reports comprises judgments with headnotes and catchwords indicating the area of law and key issues of the case prepared by legally qualified editorsFind AllER Reports
- Cases related to this particular case that are related to, or discuss this caseView related cases
- Commentary discussing this particular case from LexisLibrary's comprehensive range of titles including Butterworths, Halsbury's and TolleyView related commentary