| Source: | All England Reporter |
| Publisher Citation: | [2003] All ER (D) 548 (Jul) |
| Court: | Technology and Construction Court |
| Judge: | Recorder Storey QC |
| Representation | Finola O'Farrell QC (instructed by Kath Nicholson) for the claimant. |
| James Howells (instructed by DLA) for the defendant. | |
| Judgment Dates: | 31 July 2003 |
Catchwords
Limitation of actions - Limitation period - Time from which period runs - Tort - Accrual of damage.
The Case
In all the circumstances, the claimant's claims in tort against the defendant who had supplied materials to the sub-contractor under the main contract that the claimant had entered into with a third party as main contractor for certain works to be carried out were out of time.
Practice Areas
If you are a LexisLibrary subscriber you can read more about this case here.
Lexis®Library
- The All England Law Reports comprises judgments with headnotes and catchwords indicating the area of law and key issues of the case prepared by legally qualified editorsFind AllER Reports
- Cases related to this particular case that are related to, or discuss this caseView related cases
- Commentary discussing this particular case from LexisLibrary's comprehensive range of titles including Butterworths, Halsbury's and TolleyView related commentary